1 Locate pipe
2 Install temporary by-pass through water meters or garden spigots
3 Excavate access pits at each end of the section
4 Clean pipe with metal chain reamer
5 Closed-Circuit Television (CCTV) inspection to chain the service connections
6 With specialized robotic equipment, insert plug in every service connection from inside the pipe
7 Impregnate liner on-site in a refer truck by injecting the epoxy between the two layers of liner while pulling the liner in place
8 Form the liner by sending swabs from one end to the other
9 Circulate hot water for curing
10 Perform hydrostatic pressure test
11 Reinstate service connections by drilling with specialized robotic equipment from inside the pipe
12 Disinfect the pipe
13 Reconnect the water distribution system
14 Remove temporary by-pass
15 Restore sitem